Road Closure of Vine Cactus Road as part of the Hard Road Resurfacing Project

340

 

PHILIPSBURG, Sint Maarten — The Ministry of VROMI (Public Housing, Spatial Planning, Environment & Infrastructure) hereby announces the commencement of the Vine Cactus Road, Sucker Garden repairs, which is part of the ongoing Hard Road Resurfacing Project.

Please be advised that Vine Cactus Road will be fully closed for works from October 2nd to October 11th, 2024, between the hours of 8:00 AM and 4:00 PM daily. Access to the area will be maintained through the Arch Road entrance.

The works will be carried out by Omega Construction, with concrete supplied by Sint Maarten Concrete. We kindly request that the public remain cautious and vigilant of the workers as they complete their tasks.

Important Details:

  • Date & Time: October 2nd to October 11th, 2024, from 8:00 AM to 4:00 PM
  • Detour: Entrance through Arch Road
  • Contractor: Omega Construction
  • Concrete Supplier: Sint Maarten Concrete

We thank you for your cooperation and understanding as we work to improve our infrastructure.